Tim Bracken, wtop.com
The late-morning commute could be a headache for drivers on Route 7 between Sterling and Tysons Corner today.
Workers with the Dulles Corridor Metrorail Project will be transporting large assembly structures for a traction power substation to a site south of the Dulles Toll Road, near The Barns of Wolf Trap. The trucks will be traveling between Sterling and Trap Road between the hours of 9:30 a.m. and 3:30 p.m. today through Thursday.
Here’s what you need to know:
Tuesday and Wednesday:
- Trucks carrying elements of the traction power substation will move out of Sterling on northbound Route 28 to N. Sterling Boulevard, then east on Route 7 to Trap Road.
Thursday:
- Crews will move a disassembled large crane from the work site, traveling west on Route 7, then south on Route 28 to a staging area at Dulles Airport
Follow WTOP Traffic on Twitter.
(Copyright 2012 by WTOP. All Rights Reserved.)