Plastic pipes from I-395 bridge washed away into Four Mile Run

Several plastic pipes washed away from a construction project on the I-395 bridge into Four Mile Run after a downpour of rain Sunday.

The I-395 project between the Shirlington interchange and Glebe Road currently uses 35 plastic pipes to redirect water in Four Mile Run away from the work area. The rain’s movement of the pipes did not harm the construction project, said Jennifer McCord, a Virginia Department of Transportation spokesperson.

Workers are currently moving the pipes out of the creek by hand and should be done with the removal sometime today or tomorrow, McCord said. She added that she is unsure if the pipes will be put back into place as they may no longer be needed for the project.

The project costing $7.2 million should be complete by November 2018, she said.

Photos by Mark Wigfield

Federal News Network Logo
Log in to your WTOP account for notifications and alerts customized for you.

Sign up