Sponsored by Navy Federal Credit Union
TRAFFIC ALERT In Anne Arundel County, all lanes are blocked on eastbound MD 100 after Arundel Mills Boulevard (Exit #10) because of a crash.

Phase 2 of Silver Line to begin next month

WASHINGTON – As construction is set to wrap up this fall on Phase 1 of the Silver Line, work will begin next month on Phase 2, extending Metro into Loudoun County.

Clark Construction recently won a bid for $1.2 billion to build the second phase from Reston Town Center thru Dulles Airport to Ashburn.

The full cost of Phase 2 will be about $2.6 billion, says project director Sam Carnaggio. He expects phase two to be completed in five years, with passenger service in January 2019.

Carnaggio predicts “lots of survey work over the next six months,” with visual signs of progress on Phase 2 at the beginning of the year.