I-95 bridge project completed early, under budget

RICHMOND, Va. (AP) — Virginia highway officials say the restoration of 11 bridges on Interstate 95 in the Richmond area was completed three months early and $16 million under budget.

The Richmond Times-Dispatch reports (http://bit.ly/1qEfmqJ ) that a major reason for the efficient completion of the project was the off-site construction of concrete components. Virginia Department of Transportation spokesman Lindsey LeGrand says the sections were cast in a work yard in Hanover County and moved into place like puzzle pieces. The biggest piece of the puzzle was a bridge in Richmond that required 88 pre-cast bridge sections.

The project, which began in September 2010 and ended up costing $90 million, covered a seven-mile stretch of I-95 in Richmond and Henrico County that handles nearly 160,000 vehicles a day.

___

Information from: Richmond Times-Dispatch, http://www.timesdispatch.com

Copyright 2014 The Associated Press. All rights reserved. This material may not be published, broadcast, rewritten or redistributed.

Federal News Network Logo
Log in to your WTOP account for notifications and alerts customized for you.

Sign up