A look at overruns at Brasilia Cup stadium

The Associated Press

Some examples of questionable costs that government auditors found in the building of Brasilia’s stadium for the World Cup:

–Auditors allege that nearly one-third of the $900 million in costs for the stadium are fraudulent.

–The tab for transportation of prefabricated grandstands in Brasilia was supposed to be just $4,700, but the construction consortium billed the government $1.5 million.

–$16 million was lost when Brasilia’s city government inexplicably failed to enforce a fine against the consortium building the stadium despite a five-month delay in completion of the main portion of the arena.

–Materials worth $2.3 million were listed multiple times on bills.

Copyright 2014 The Associated Press. All rights reserved. This material may not be published, broadcast, rewritten or redistributed.