Annual Paving Project Moves Into Clarendon

Construction in Clarendon Construction in Clarendon Construction on Wilson Blvd in Clarendon Construction in Clarendon

Driving through Clarendon has become messier and is taking longer due to construction on several of the major roads in the neighborhood. It’s the latest area to be worked on as part of the annual paving program.

The affected area in Clarendon covers about five blocks — two along Wilson Blvd, two on N. Highland Street and one on N. Fillmore Street. Crews have been milling — removing the top layer of streets — and adjusting utilities as needed. Paving with two to three inches of hot-mix asphalt follows soon after, as well as line painting.

Because of the busy nature of the Clarendon neighborhood, contractors plan to do the paving portion on Sunday and Monday nights, weather permitting. Crews have been able to do the milling and utility adjustments during the day because those tasks are more flexible in terms of working around vehicle and pedestrian traffic.

Clarendon isn’t the only area getting repaved; an online map highlights in red the active paving projects throughout the county. Residents in the affected areas receive letters announcing the road work four to six week before it begins. Temporary “no parking” signs are posted along the roads and cars parked in the work areas during the restricted times will be towed.

The county’s annual paving program typically takes place between March and October because the hot-mix asphalt can only be applied in warm, dry weather. Currently, this year’s paving stands at about 87 percent complete.